Nayara Energy Vadinar Refinery: Snatch Blocks, Wire Rope and Stud Link Chain

Nayara Energy Vadinar Refinery: Snatch Blocks, Wire Rope and Stud Link Chain

By Sealinkers Engineering · Rigging & Lifting Engineering Team16 November 20267 min read

A 20 MMTPA refinery that keeps growing on the Gulf of Kutch

Nayara Energy's refinery at Vadinar, in Gujarat's Devbhumi Dwarka district, began commercial production in May 2008 at 10.5 million tonnes a year. It has since grown to 20 million tonnes, about 400,000 barrels a day [1][2][4], and its Nelson complexity index has risen from 6.1 to 11.8 [2]. In 2024 Nayara added a 450,000 tonne-a-year polypropylene plant at the site, its first polypropylene unit [3]. In 2026 the refinery went through a planned maintenance shutdown of about 35 days [4], the kind of turnaround that keeps a complex refinery running safely between overhauls.

In 2025–26, Sealinkers supplied the Vadinar refinery directly with Crosby snatch blocks, wire rope and stud link chain. This case study describes the refinery and its marine terminal, what we supplied, and what snatch blocks and maintenance lifting at a refinery ask of the buyer. Supply details come from our own order and dispatch records; project facts are cited to public sources listed at the end.

The refinery and its marine terminal

  • Capacity. 20 MMTPA of crude processing [1], or about 400,000 barrels a day [4].
  • Growth. Capacity rose from 10.5 to 20 MMTPA and complexity from 6.1 to 11.8 over a period of four years [2]. Nayara has also planned a further expansion to 46 MMTPA with petrochemical units [1].
  • Polypropylene. The 450,000 tpy polypropylene plant started up in 2024. It uses UNIPOL PP process technology and catalysts from W. R. Grace [3].
  • Power. A 1,010 MW captive power plant supplies the refinery with power and steam [2].
  • Crude in. A single point mooring of the catenary anchor leg (CALM) type sits in about 35 m of water in the Gulf of Kutch. It takes tankers of up to 350,000 DWT and connects to the crude tank farm through a 48-inch pipeline about 19 km long [1].
  • Product out. Two product berths in the Pathfinder Inlet take ships of up to 100,000 DWT. Each is linked to the refinery's product tanks by a pipeline of about 21 km [1]. The SPM is designed for 27 MMTPA and the two berths for 14 MMTPA, and the terminal works around the clock [1].

How Sealinkers supported Nayara Energy

Between 2025 and 2026, Sealinkers supplied Nayara Energy directly at the Vadinar refinery site, against Nayara's own purchase orders:

  • Crosby snatch blocks: model 419 at 15 t and model 431 at 30 t, from our blocks and sheaves range.
  • Usha Martin 38 mm wire rope in 6x36 steel-core construction.
  • 42 mm U2-grade stud link chain.

The order is small next to the refinery's scale, but it shows the kind of supply a maintenance team needs. Each block is made for one rope size, the rope is supplied with its certificate, and the chain comes graded and proof-loaded. Most of this article is about getting those details right.

What snatch blocks and refinery maintenance ask of rigging

A snatch block carries more than the line pull

A snatch block has a side plate that opens, so a rope can be laid into it at any point along its length without threading the end through. That makes it the usual way to turn a winch or crane rope around a column, pipe rack or structure. The load on the block, and on whatever the block hangs from, depends on the angle between the two rope legs:

Included angle between rope legsLoad on block, as a multiple of line pull
0° (legs parallel, rope turns 180°)2.00
60°1.73
90°1.41
120°1.00
150°0.52

A 15 t snatch block with the rope turning back on itself can therefore take a line pull of only 7.5 t. The anchor point, beam clamp or sling it hangs from has to take the full 15 t, in the direction of the resultant. That is why the block's rating, its attachment and its anchor are checked together. The rated load of a block is the load on its hook or shackle, not the pull in the rope.

Match the sheave to the rope

Every snatch block is designed for a particular rope diameter. The sheave groove is cut slightly larger than that rope so the rope is supported over about a third of its circumference. Two mistakes are common:

  • 1. Rope too large for the groove. The rope is pinched, its strands are crushed and it wears quickly at the groove edges.
  • 2. Rope too small for the groove. The rope flattens into the wide groove and loses support, which shortens its fatigue life.

The other ratio that matters is D/d, the sheave tread diameter divided by the rope diameter. The 15 t block we supplied has a 457 mm sheave for 26 mm rope, a D/d of about 17.5. The 30 t block has a 508 mm sheave for 32 mm rope, about 16. At those ratios a 6x36 rope keeps roughly nine-tenths of its straight-line strength over the sheave, by general industry guidance. The ratio is also why large-diameter rope should never be forced through a small block. Our wire rope construction guide explains why 6x36 ropes cope better with bending than 6x19.

Turnaround lifting: plan the gear before the shutdown

A refinery turnaround packs months of work into a few weeks. Heat-exchanger bundles are pulled, column internals and trays are lowered through manways, valves and pumps are swapped, and new equipment is set in congested units. Most of these lifts use snatch blocks, chain blocks, winches and short slings rather than big cranes. Good practice before a shutdown is to:

  • 1. Inspect and tag every item in the gear store, and quarantine anything without a current certificate or with a damaged latch, sheave or side plate.
  • 2. Order replacements early, by make, model, capacity and rope size, so the new blocks match the ropes already on the winches.
  • 3. Check anchor points for the resultant load, not just the line pull.
  • 4. Brief the riggers on the latch and side plate. A side plate that is not locked, or a hook latch that is tied back, is a common cause of dropped rope.

Chain at a marine terminal

A refinery fed through an SPM and served by product jetties also needs marine chain. Terminals use stud link chain in buoy and mooring systems, where it must match the grade and diameter of the system it joins. U2 is a higher-strength grade than U1, and each length is proof-loaded before dispatch. When you replace chain, match the grade as well as the diameter, and keep the certificate with the asset record. Our anchor chain selection guide explains the grades.

Lessons for refinery maintenance buyers

  • 1. Specify snatch blocks by capacity, rope size and attachment (hook or shackle), and check the rope size against the winch rope.
  • 2. Rate the anchor for the resultant, using the angle table above.
  • 3. Keep D/d in view. A block with a small sheave shortens rope life even when its rating is adequate.
  • 4. Buy before the turnaround, not during it, and ask for test certificates with the dispatch. See how to read a test certificate.

Frequently asked questions

What did Sealinkers supply to Nayara Energy's Vadinar refinery?

In 2025–26 we supplied Crosby 419 and 431 snatch blocks at 15 t and 30 t, Usha Martin 38 mm 6x36 wire rope and 42 mm U2-grade stud link chain, directly to the refinery site at Vadinar.

How do I work out the load on a snatch block?

Multiply the line pull by the factor for the angle between the two rope legs: 2.0 when the legs are parallel, 1.41 at 90°, 1.0 at 120°. The result is the load on the block and on its anchor point, and it must not exceed the block's rated load.

Can I run a larger rope through a snatch block?

No. A block is made for a stated rope diameter. A larger rope is pinched in the groove and crushed, and it can jump the sheave. Choose the block for the rope.

Do you supply snatch blocks other than Crosby?

Yes. We supply Crosby McKissick blocks and other makes in hook and shackle versions. Tell us the rope diameter, the line pull and the attachment you need, and we will propose a model.

Preparing for a shutdown?

Send us your turnaround rigging list or the winch and rope details for the job. We will quote matched snatch blocks, wire rope, slings and chain, with certificates. Contact Sealinkers, or see our Crosby range.

Sources

  • [1] Coviva Energy Terminals Ltd (a Nayara Energy subsidiary), brief summary of the proposed single point mooring at the Offshore Oil Terminal, Vadinar, environmental clearance filing, August 2019 — environmentclearance.nic.in
  • [2] NS Energy, Vadinar refinery project profile, 9 September 2022 — nsenergybusiness.com
  • [3] Hydrocarbon Engineering, "Grace expands polypropylene operating capacity in India with Nayara Energy Ltd", 30 October 2024 — hydrocarbonengineering.com
  • [4] Quantum Commodity Intelligence, report on a 35-day maintenance shutdown at Nayara's Vadinar refinery, 26 March 2026 — qcintel.com

Cover photo: Vadinar refinery, then operated as Essar Oil, October 2008, by Abhisek Sarda, Wikimedia Commons, CC BY 2.0. Photos are resized and are not endorsed by their authors.

Share this guide

Related Guides

Ready to put this into practice?

Every item ships certified, and our in-house test house backs it with the paperwork.

Sealinkers Engineering

Rigging & Lifting Engineering Team

Sealinkers has supplied and certified rigging, lifting and mooring equipment from Darukhana, Mumbai since 1977. These guides are written and checked by the engineers who specify this gear and proof-load it on our own test bed.

  • in-house test house — proof-load bed from 1 to 1,200 tonnes
  • Proof-load testing and certification in-house since 1977, Darukhana, Mumbai
  • Class-society interfaces: IRS, ABS, LRS and BV