Mumbai Metro Line 4 and 4A: heavy lifts on the road to Thane
In a single night in June 2025, eight U-girders of about 98 tonnes each, 783 tonnes in all, were erected at Kapurbawdi station in Thane. The job used one 550-tonne crane, three 500-tonne cranes, four multi-axle trailers and a crew of more than 90, including 28 riggers, on the busy Ghodbunder Road corridor [2]. Two months earlier, a 540-tonne, 62.7 m steel girder had been set 24 m above the JVLR–LBS junction at Gandhi Nagar, Vikhroli, in three stages, threaded under the Metro Line 6 viaduct. It is now the top level of a four-level stack of road, flyover and two metro lines [3]. In February 2026, three steel spans totalling 325 tonnes went up at Bhandup West in two nights instead of the four planned, using eight heavy cranes and 12 multi-axle trailers [4].
These are the Mumbai Metropolitan Region Development Authority's (MMRDA's) milestones on Metro Line 4 and its extension, Line 4A: the elevated Green Line from Wadala through Ghatkopar to Kasarvadavali and on to Gaimukh [1]. In 2025 Sealinkers supplied lifting gear to the corridor, chiefly to a casting yard on Line 4 package CA-12 at Kolshet, Thane. This case study covers the corridor, our supply, and what a U-girder viaduct asks of its rigging.
The project: 35 km of elevated metro to Gaimukh
- Length and stations. Line 4 is 32.32 km and Line 4A is 2.88 km, together about 35.2 km of elevated viaduct with 34 stations [1].
- Package CA-12. The Thane section from Kapurbawdi to Kasarvadavali: about 6.8 km of viaduct and six stations [1]. Kapurbawdi will interchange with Metro Line 5 [7].
- Line 4A, package CA-54. The 2.88 km northern extension from Kasarvadavali to Gaimukh, with stations at Gowniwada and Gaimukh. It was awarded to J. Kumar Infraprojects in September 2019 for Rs 342 crore. J. Kumar launched the first of the extension's 296 U-girders on Ghodbunder Road in March 2021 [1][6].
- Depot. Mogharpada, a 20-hectare site serving the corridor [1].
- Progress. Physical progress was 89.02% in December 2025 [4]. The first phase, about 10.5 km and ten stations from Gaimukh to Cadbury Junction, is targeted to open in December 2026 [5]. In October and November 2026, metro coaches were being lowered onto the viaduct between Modella Naka and Teen Hath Naka under midnight-to-5 am traffic diversions [7].
How Sealinkers supported the Line 4 corridor
Our supply to the corridor in 2025 went to two sites:
- Line 4, package CA-12, Kolshet (Thane): a subcontractor's casting yard, supplied with heavy wire rope slings up to 76 mm and 80 tonnes SWL, alloy chain slings, shackles and polyester webbing slings.
- Line 4A, package CA-54, Kasarvadavali: J. Kumar Infraprojects' site, supplied with wire rope slings.
Our slings are made at our own works and proof-load tested in our in-house test house, and each ships with its test certificate. The heavy lifts described above are MMRDA's milestones on other parts of the corridor. Our supply went to the casting yard and site stores listed here, and we do not claim any particular lift for our equipment.
What a U-girder viaduct asks of its rigging
The casting yard: one girder, many lifts
A U-girder is a full span cast in one piece, with the trough that will carry the track already formed. At around 98 tonnes for the Kapurbawdi girders [2], it is a heavy precast element. In general practice, a U-girder is lifted several times between mould and pier: stripped and lifted out of the mould, moved to the curing and storage stack, lifted onto a multi-axle trailer, and finally lifted into place by cranes at the pier. Every one of those lifts uses the girder's designed lifting points, and every one needs sling sets of matched length so the girder stays level and is not twisted. A yard doing this every day wears slings out quickly. Plan inspection by the number of lifts, and replace sets, not single legs. See wire rope discard criteria for when a sling must come out of service.
Night erection on Ghodbunder Road
The Kapurbawdi operation fitted eight girders into one night by bringing four large cranes, trailers, counterweight trailers and more than 90 people to one junction [2]. In general practice, a night like that only works if the rigging is ready before the traffic is stopped. Sling sets and shackles for each girder are made up and inspected in advance and labelled by girder and crane. Spares go on the site, and certificates are checked against tags before the window opens. A wrongly sized shackle or a missing certificate found at midnight can cost the whole night. For the shackle checks, see the shackle size selection guide.
Steel spans over junctions
Where a concrete span cannot fit, MMRDA has used heavy steel girders: 540 tonnes at Gandhi Nagar in three stages [3], and 325 tonnes in three spans at Bhandup [4]. In general practice, steel spans of this size are lifted by several cranes or launched in stages. The rigging is designed for the load share each crane carries at every stage, not just the average, and attachment points are fabricated lugs, not slings around the steel. Painted steel needs edge protection wherever a sling or tag line touches it. The sling-angle effects that matter on any multi-leg lift are set out in sling angle effects on SWL.
Lessons for buyers on a U-girder line
- 1. Rig to the girder's lifting design. Use the lifting points and sling geometry the designer specified, and get sling sets made to those lengths.
- 2. Separate yard and site sets. A casting yard and a launching site use different sling lengths and see different wear. Keep separate sets and separate records for each.
- 3. Make up night-lift rigging in daylight. Assemble, inspect, label and certify each girder's rig before the traffic window, and keep spares at the crane.
- 4. Use webbing where the finish matters. Polyester webbing slings with sleeves protect finished concrete edges and painted steel. Keep wire rope for raw lifts.
- 5. Track certificates by tag number. On a long corridor with many contractors, a sling without a traceable certificate cannot be used. Our guide on how to read a test certificate explains what to check.
Frequently asked questions
What did Sealinkers supply on Line 4?
In 2025 we supplied a subcontractor's casting yard on package CA-12 at Kolshet, Thane, with heavy wire rope slings up to 76 mm and 80 tonnes SWL, alloy chain slings, shackles and polyester webbing slings. A smaller supply of wire rope slings went to the Line 4A site listed above.
Did Sealinkers equipment lift the 540-tonne Gandhi Nagar girder?
No such claim is made. The Gandhi Nagar, Bhandup and Kapurbawdi lifts are MMRDA's milestones on the corridor. Our supply went to the casting yard and site named above.
How many times is a U-girder lifted before it is in place?
Typically several times: out of the mould, into storage, onto the trailer and onto the piers. That is why casting-yard slings wear faster than site slings and should be inspected and replaced on a schedule.
Are your slings tested and certified?
Yes. Our slings are proof-load tested at our in-house test house, which has a 1,200 T proof-load test bed, and each item ships with its certificate. Class-society inspection by IRS, ABS, LRS or BV can be arranged.
Running a casting yard or girder launch?
Send us your girder weights, lifting-point layout and crane plan, and we will propose matched sling sets and shackles to suit, with certificates. Contact Sealinkers, or browse wire rope slings.
Sources
- [1] The Metro Rail Guy, Mumbai Metro Green Line: info, route map, tenders and updates, updated 14 September 2025 — themetrorailguy.com
- [2] Free Press Journal, Metro Line 4 overnight erection of 8 U-girders at Kapurbawdi station, 2 June 2025 — freepressjournal.in
- [3] Free Press Journal, 540-tonne girder installation at Gandhi Nagar junction, Metro Line 4, 28 April 2025 — freepressjournal.in
- [4] Free Press Journal, Metro Line 4: 325-tonne steel spans launched at Bhandup West, 3 February 2026 — freepressjournal.in
- [5] Swarajya, Thane Metro Line 4 first phase from Gaimukh to Cadbury Junction set to open in December 2026, 27 October 2026 — swarajyamag.com
- [6] The Metro Rail Guy, Mumbai Metro Line-4A's 1st U-girder launched by J Kumar, 12 March 2021 — themetrorailguy.com
- [7] Free Press Journal, Thane Metro Line 4 construction gains momentum, services likely to begin by December, 22 October 2026 — freepressjournal.in
Related Guides
Ready to put this into practice?
Every item ships certified, and our in-house test house backs it with the paperwork.
Sealinkers Engineering
Rigging & Lifting Engineering Team
Sealinkers has supplied and certified rigging, lifting and mooring equipment from Darukhana, Mumbai since 1977. These guides are written and checked by the engineers who specify this gear and proof-load it on our own test bed.
- in-house test house — proof-load bed from 1 to 1,200 tonnes
- Proof-load testing and certification in-house since 1977, Darukhana, Mumbai
- Class-society interfaces: IRS, ABS, LRS and BV