Sealinkers on LinkedIn
Nuclear Dome Lifts: The Rigging Engineering Challenge

Nuclear Dome Lifts: The Rigging Engineering Challenge

By Sealinkers Engineering · Rigging & Lifting Engineering Team22 May 2021Last reviewed 16 November 20266 min read

Nuclear containment dome lifts: the rigging engineering challenge

Placing the steel liner of a reactor's inner containment dome is one of the most demanding single lifts in Indian heavy engineering. At the Kakrapar Atomic Power Project in Gujarat — India's first pair of indigenously designed 700 MWe pressurised heavy water reactors, units 3 and 4 — NPCIL lifted each dome liner as one piece rather than erecting it panel by panel at height [1][2]. This article explains how that lift was engineered, what it asks of the rigging between the hook and the load, and what buyers of heavy-lift gear can learn from it.

Sealinkers supplied Larsen & Toubro, the main civil contractor for Kakrapar units 3 and 4 [3], with wire rope pulling-and-lifting machines and 10-tonne chain pulley blocks for the KAPP-3&4 site in 2021. The dome lifts themselves were NPCIL's engineering; the details below are from NPCIL's and the crane maker's published accounts.

What was lifted at Kakrapar

The inner containment dome liner at Kakrapar is a self-supporting, double-curved steel dome 46 m in diameter and 8 m high, with two large openings left for any future steam generator replacement [1]. It was fabricated on the ground from 53 panels of ten types, using 33 jigs and more than 200 full-scale templates, with backing members of ISHB-150 sections bent to curvature [1]. Before the lift, the containment spray system and the hydrogen and steam-conditioning monitoring systems were pre-installed on the dome, so they would not have to be fitted at height later [1].

On 27 November 2017, NPCIL lifted the unit 4 dome assembly in a single lift with a Liebherr LR 11350 crawler crane, a machine of 1,350 tonnes maximum capacity [1][4]. The hook load was 365 tonnes, including the dome structure, the pre-installed systems, the tools and tackles, and the evener beam [1]. With that lift, NPCIL said, the Kakrapar project had completed the lifting and erection of the entire dome assemblies of both units [1].

The same crane had already made an unusual lift at Kakrapar: in December 2013 it lifted a preformed steel ring liner of about 50 m diameter for unit 3's inner containment wall, with a total crane load of about 172 tonnes including an evener beam and a load-tested spider frame [4][5].

Drone view of Kakrapar unit 3 reactor building under construction with a Liebherr LR 11350 crawler crane
Kakrapar units 3 and 4 under construction, June 2016, with the Liebherr LR 11350 crawler crane beside the unit 3 reactor building. Photo: Reetesh Chaurasia, Wikimedia Commons, CC BY-SA 4.0.

Why a dome is lifted in one piece

Erecting a dome panel by panel means welding at height, on curved surfaces, with every panel needing its own temporary support until the shell closes. Lifting the assembled dome in one piece moves almost all of that work to the ground, where it can be jigged, welded, inspected and fitted out under controlled conditions. The price is a single, very heavy and very large lift that has to be right first time: the load is wide, flexible and sensitive to wind, and it must land on a prepared ring at height within tight tolerances.

The rigging between the hook and the dome

NPCIL's accounts name the main elements between the crane hook and the load: an evener beam, a spider (strong-back) frame and the "tools and tackles" connecting them [1][5]. Each element does a specific job.

The evener beam

An evener (or equaliser) beam hangs from the hook and distributes the load between rigging legs so that each carries its intended share. On a wide, flexible structure such as a dome, uneven leg loads would distort the shell; the beam keeps the geometry under control.

The spider frame

A spider frame spreads the pick points over the dome's circumference, so the structure is lifted from many points at once rather than a few. At Kakrapar the spider frame used for the ring liner was load-tested to 140 tonnes before use [5].

Between the frame and the dome, and between the beam and the hook, the connections are wire rope slings, shackles and master links. On a lift of this consequence every one of them needs a rated working load, a traceable test certificate and a recent thorough examination. Lengths are matched so the load hangs level, and shackles are chosen to suit both the sling eye and the lifting lug.

Level and stress checks before the lift

Before the unit 4 lift, the assembly was raised about 1 m off the ground twice — for half an hour and then for two hours — to let stresses settle and to check that it hung level [1]. That practice tests the rigging under the real load while the dome is still a metre from the ground, which is the safest place to find a problem.

Rigging considerations for extreme single lifts

  • Higher margins than routine work. Lifts of this consequence are planned with margins well above the minimum used for everyday lifting, and every item in the rigging chain is individually certified and traceable.
  • Load monitoring. Load cells or load-monitoring shackles show the actual load on each leg during the lift, so an unexpected shift is caught early.
  • Weather windows. A large shell is sensitive to wind, so lifts are attempted only in a defined wind-speed window.
  • Trial lifts. Lifting just clear of the ground and holding, as at Kakrapar, proves the rigging and the load's behaviour before height is gained.

Where certified rigging gear fits

Every component in a lift like this — wire rope slings, shackles, master links, load cells — needs a valid, traceable test certificate. Sealinkers' in-house test house proof-load tests slings and assemblies on a 1,200 T proof-load test bed and issues certificates with each item; see proof-load testing and how to read a test certificate. For how sling angle changes the load on each leg, see our guide to sling angle and SWL.

Frequently asked questions

How heavy was the Kakrapar dome lift?

NPCIL reported a hook load of 365 tonnes for the unit 4 inner containment dome lift on 27 November 2017, including the dome structure, pre-installed systems, tools and tackles and the evener beam.

Which crane lifted the Kakrapar dome?

A Liebherr LR 11350 crawler crane, with a maximum capacity of 1,350 tonnes.

What is an evener beam?

An evener or equaliser beam hangs from the crane hook and divides the load between rigging legs in a controlled way, so that a wide or flexible load is not distorted by unequal leg loads.

What did Sealinkers supply at Kakrapar?

In 2021 we supplied Larsen & Toubro at the KAPP-3&4 site with wire rope pulling-and-lifting machines and 10-tonne chain pulley blocks.

Planning a critical lift?

For certified heavy-lift slings, shackles and master links, or advice on rigging a high-consequence lift, contact Sealinkers. See also our case studies on Kaiga Units 5 & 6 and Kudankulam Units 3 & 4.

Sources

  • [1] NPCIL, "Inner containment dome structure lifting and erection (as a single unit) successfully completed at KAPP-4", 28 November 2017 — npcil.nic.in
  • [2] World Nuclear News, "India's Kakrapar 3 begins commercial operation", June 2023 — world-nuclear-news.org
  • [3] World Nuclear News, "Kakrapar civil works contract for L&T" — world-nuclear-news.org
  • [4] Liebherr, LR 11350 crawler crane moves ring liner in India, May 2014 — liebherr.com
  • [5] Equipment India, "Implementation of PRL at KAPP-3", 14 May 2014 — equipmentindia.com
Share this guide

Related Guides

Ready to put this into practice?

Every item ships certified, and our in-house test house backs it with the paperwork.

Sealinkers Engineering

Rigging & Lifting Engineering Team

Sealinkers has supplied and certified rigging, lifting and mooring equipment from Darukhana, Mumbai since 1977. These guides are written and checked by the engineers who specify this gear and proof-load it on our own test bed.

  • in-house test house — proof-load bed from 1 to 1,200 tonnes
  • Proof-load testing and certification in-house since 1977, Darukhana, Mumbai
  • Class-society interfaces: IRS, ABS, LRS and BV